Plan B Model 15 VCO status update

2004-08-12 by (i think you can figure that out)

All,

Just wanted to give you the heads up on the VCO project.  I've 
now received the PCB art for inspection and approval prior to 
making the boards.  As it turned out, the design was a lot more 
involved than we originally speculated and we can expect a two 
week delay on deliveries form the time frame originally forcast.

I will keep you all posted as the process progresses.