Plan B Model 15 VCO - update

2004-10-02 by (i think you can figure that out)

The Plan B Model 15 VCO printed circuit board sets are 
completed and will ship to me early next week.  I should have 
them in a week's time.

I'm then building two prototypes - one running from +/-15, one 
running from  +/- 12 volts.  I will use these two as my first article 
'gold'; samples during the first production run.  These two 
samples will be finished production units and will ship as well 
as soon as the first run is completed. 

Long story short, production shipments should begin in about 10 
days.  They will be fulfilled in the order received and those of you 
who paid only s 50% down will be contacted one week in 
advance before the unit is complete, giving you a week to send 
the balance.  

Thanks for your patience - the fun begins!

- P